Refrigerant work on commercial refrigeration follows the F-Gas rules: leaks are found and repaired before recharging, systems are tested before charging, refrigerant is recovered when circuits are opened and records are kept.
Vacuum and decay testing
A vacuum test proves the circuit is dry and tight after evacuation. The pump is isolated and the vacuum watched with a micron gauge: a steady reading shows the system is ready; a slow rise that levels off suggests moisture still boiling off; a continuous rise points to a leak.
It complements, but does not replace, a nitrogen pressure test, which checks strength and tightness at pressure.
High-GWP refrigerants
Since 2020, virgin HFCs with a GWP of 2,500 or more cannot be used to service refrigeration systems with charges of 40 tonnes CO₂ equivalent or more; reclaimed or recycled refrigerant remains an option under the rules.
Records
Operators keep records of checks, leaks, repairs and refrigerant added or recovered for at least five years.
Other guides on refrigerant work on refrigeration systems
- Acoustic Leak Detection
- Central Heating Leak Detection
- Concealed Toilet Cistern Leaking
- Hidden Water Leak Detection
- Mains Water Leak Detection
- Mains Water Leak Repair
- Megaflo Expansion Vessel Recharge
- Non Destructive Leak Detection
Common questions on refrigerant work on refrigeration systems are answered on the Refrigerant Reclaim page.
Choosing the right visit
Describe the equipment and what you need — a repair, a service, an inspection or a quote for new equipment — so the visit is scoped correctly and the right engineer attends.
- The outcome you need from the visit
- Equipment details and access
- How findings will be reported
Engineer labour is £120 + VAT per hour with a one-hour minimum; parts and refrigerant are quoted in writing before they are fitted.
How each type of visit works and all rates · What to have ready when you book · How we work